Related Articles

 

Grooming & Maintaining Synthetic Fields: Strategies and Tactics - With the increasing installation and use of synthetic...

 

Sustainability at Furman University: The Repurposed Shi Center - At Furman University in Greenville, South Carolina, the...

 

Permeable Clay Pavers Solve Stormwater Issues, While Preserving Historic Character of College Campuses - No matter what your status is at a private college, from a...

 

Dartmouth Basketball's Shooting Touch - In the creation of space meant to showcase a sports...

 

Climbing Walls Build Community - A university recreation center is built with the desire to...

 

Major Upgrades to Middlebury College Athletics Complex - Middlebury College has completed a major construction...

 

A Unique Path to Enlightenment - As the U.S. Department of Energy's Better Buildings...

 

Windows and Doors Deliver Reliable Performance, Lasting Impressions - Universities across the nation are seeking ever-larger...

 

State of Facilities in Higher Education - Private college and university leaders have a huge, often...

 

Scan Before You Replace: Non-Destructive Moisture Tests Provide Valuable Information for Roofing Professionals - Advanced imaging techniques provide crucial information for...

 

Bradley University Surrounds Facilities with School Spirit - Many players, coaches and athletic directors can agree that...

 

The Greenest College Residence Hall in the World - Sustainable construction requires both foresight and the...

 

Campus Paving Projects - For anyone who makes purchases for colleges in these times...

 

Protecting Student Belongings as Part of Campus Security Plan - Student security lives at or near the top of every...

 

Water Quality Testing in Aquatic Facilities - Good water quality is important for the health and well...

 

The Natatorium Puzzle: Five Warning Signs - When designing, improving, or maintaining a natatorium, you...

 

Safety, Sustainability, and Branding in University Athletics - The key to sound decision making often is not what you know...

 

Modular Buildings: Protecting Campus Image and Ensuring ADA Guidelines - In the current financial environment, budget is paramount....

 

The Climbing Wall RFP Primer - While climbing walls are becoming more common, the planning...

 

A Transformational Project: Converse College's Johnson Plaza - Many students arriving for the first time at Converse...

 

BIM & Daylighting: The Ultimate Planning and Sustainability Duo - Construction has become increasingly complex, with the need...

 

Setting the Stage for Acoustics First - Early acoustical theaters were just that--acoustic. The...

 

Upgrading Campus History: Windows Provide Green Update to Older Structures - According to the United States Census Bureau, there are...

 

Cost Considerations in the Quest for Quiet - While architects usually concentrate on the visual and...

 

Installing Synthetic Turf - The quality of synthetic turf has improved dramatically...

 

Single-Source Responsibility: An Innovative Way to Build College Sports, Fitness and Recreation Facilities - While schools wrestled with how to build a new athletic...

 

Construction of an Indoor Athletic Training Facility - One of the newest facilities on campus has a very...

 

Indoor Track and Field Enjoys a Moment in Unlikely Space - Last winter, a six-lane, 200-meter indoor banked track...

 

Modern Acoustical Design: No Longer Forced to Choose Between Good Looks and Good Sound - Over the past decade, much of what was not generally known...

 

St. Thomas University--Student Activity and Leadership Development Building - St. Thomas University's Careful Planning and Meticulous...

 

Diving Right In: Competition Venues for Aquatics - Competition venues for aquatics should have the same impact...

 

Salem College Blends New Design with Historic Island of Architecture - If Elizabeth Oesterlein were to walk up to Salem College in...

 

Cornell Implements First Solar Array to Expand Renewable Portfolio - 2MW Solar Farm Will Help Reach Carbon Neutrality: Cornell...

 

Construction and Planning: Look to Other Projects to Get Ideas for Your Own - Virtually every private college has a variation on the same...

 

Object Lesson: Campus Project Planners Must Understand New Buildings Within Campus Context - Once completed, buildings are never viewed in isolation....

 

Archives > April 2015 > Top Ten Mistakes Made in Gymnasium Design and Construction

Top Ten Mistakes Made in Gymnasium Design and Construction

Learn from others' mistakes to avoid expensive retrofits and upgrades in your next sports facility project.

By: Nik Ditzler

Careful planning, measuring, and communicating now can keep your project under budget. These are ten mistakes to watch for, when you are designing and constructing your gymnasium: 

1. Not planning for future expansion

Have you noticed that the pace of change in the sports industry is increasing exponentially? One day you're building a simple basketball facility, and next year you might be adding an NCAA emerging sport to the schedule in the same facility.

Or, a new coach might require matching practice facilities for his or her team or your athletic director may have a donor with interest in expansion to boost recruiting. Clearly, you want your new facility to meet the needs of your program now and for many years to come. Even if your budget is small, architects can design in features to allow for cost-effective future expansion if you visit with them about your organization's interest in growth and industry trends.

2. Not considering flexible spaces that could boost revenue

Wouldn't it be great to host major funders at your own facility or, better yet, rent out your facility to the community as an entertainment venue? Many gymnasiums serve dual- or multi-purposes with banquet facilities, locker rooms, and spectator facilities under one roof. If your organization sees this as a benefit, work with your design committee to incorporate these features into the blueprints.

3. Cutting corners on equipment to save money

With relatively inexpensive long-term financing available, considering the life cycle of the equipment you purchase should be a primary concern. Replacing equipment can not only be an unwelcome operating budget concern in the early years before the facility is out of the red, but is also a safety and liability concern.

No one needs to buy the most expensive option for each item, but looking at warranties and specifying trusted manufacturers with a track record in the industry can be crucial to your facility's bottom line. Examples include ordering fixed rims instead of breakaway basketball goals or glue-on backboard padding instead of molded bolt-on padding. These incremental decisions may cost three times more than the economy option but an extra $1,000 now may save replacement equipment and labor expense later.

southernmethodist4. Not designing the building with adequate support to hang goals

Ask your building manufacturer or a structural engineer if adding steel specifically for ceiling-suspended equipment such as basketball goals is recommended. Including the necessary support structure in your initial project can save money and increase product satisfaction. You don't want to be the one to explain why your projected grand opening must be delayed to allow for modifications and additions, plus the added expense of keeping the crew onsite can often be avoided with careful planning.

5. Ignoring minimum ceiling height requirements for ceiling and wall suspended systems

It isn't rocket science: Moving parts move. Imagine the spaces in front of, to the rear of, and on either side of the equipment you are hoping to include in your facility. For example, if you want rear braced systems, you will need adequate room without interference behind the backboards and goals. Support braces and cabling will also need to be taken into account, so accurate measurements and building design documents are critical.

6. Ordering too late (timing is everything)

In spite of everyone's best intentions, sometimes things fall between the proverbial cracks. When this happens, contractors' schedules may not allow for modification regardless of the fact that your equipment cannot be delivered on the original schedule. Add to your calendar the dates for final approval of design documents, confirm delivery dates with your contractor or directly with the manufacturer, and ask for tracking information for the shipment.

Custom equipment that is built to your specifications will often require two or three months from your purchase order and approval. Transit times, especially in the winter, can be as long as two weeks and not every item can be shipped using an expedited small package carrier, so plan accordingly.

7. Skipping the shipment inspection

ymca

Missing hardware, damaged finishes, and split shipments are a frustrating reality when heavy, bulky equipment is shipped across the country. It's a green concept that is also practical: order from a nearby regional manufacturer to save fuel and expense but also reduce the likelihood of damage. Reputable manufacturers should consider the most direct routes for your shipment but mistakes and losses still happen. The best time to learn of a freight-related problem is before signing for the shipment. The worst time is as the installer is on scaffolding trying to install the equipment.

8. Over- or under-communicating with the manufacturer

Remember the popular game of telephone when you were a kid? Multiply the number of cans, strings, and ears by 50-100 and you have a pretty standard sized team for most sports facility construction projects. While the manufacturer of any custom equipment may not be interested in every design change, be sure to communicate anything related to the structure, ceiling, and walls if they are providing equipment that will attach to these surfaces. Even if you are ordering all portable sports equipment, the flooring and slope may affect the suitability of equipment.

9. Ignoring expert advice

Your coaches likely have experience with many types of sports equipment and your facility manager will know the pitfalls and benefits of equipment currently in your building.

Maybe competing coaches have complimented you or chastised you about the locker rooms or the playability of your equipment. Leading manufacturers are outfitting sports facilities of many types every day and can be another source of advice as you sort through what is important to you and your audiences. Listening to industry experts is a best practice you'll hear from those who have achieved the facility ribbon-cutting phase before.

10. Not enjoying the final result

There may not be a gold statue in the entryway commemorating your involvement in this gymnasium construction project. However, pat yourself on the back for contributing to not only your organization but also your community. Sports is growing in importance in tourism budgets and tax revenue is a much-talked about benefit as well.

But, even a K-6 school with only parents as spectators serves a noble purpose and provides opportunities for fun, team-building, and future careers. Make time to get out to events at your new facility, sit down and immerse yourself in what you have created. As they say, you get out of it what you put in.

 

 

About The Author
Nik Ditzler

is Director of Bison, Inc.'s Specified Products Group, headquartered in Lincoln, Nebraska. For over 30 years, Bison and its divisions have provided innovative, safe and sustainable products to schools, park districts, rec centers and private clubs for indoor and outdoor sports and recreation activities. Details can be found at www.bisoninc.com.

 

 

 